Aurora Ave - 128th to 142nd

Description

This project includes the extension of the box culvert, storm sewer, and earthwork for the installation of a sidewalk on the south side of Aurora Avenue from 128th Street to 142nd Street. It is anticipated that this project would be completed by early September.

Project Status Update - 7/12/18

The same contractor is working on Waterford Road from 156th to 170th Street. The contractor is coordinating their efforts across both projects to accomplish both project in a timely manner. 

The contractor is currently working on grading and is hoping to accomplish the sidewalk in the month of July. 

July 18, Aurora Avenue will be closed  from the west entrance of Webster Elementary School to the east side of 138th Street.

All dates are tentative and subject to weather delays.

Please see the detour map below.